Porcupine River Bridge Removal and Replacement Underway March 4, 2024 
Plans for the replacement of the Porcupine River Bridge on Fredrick House Lake Road were finalized by council on Tuesday, February 6, 2024, with approval of the construction contract awarded to Looby Builders Ltd.

The original reinforced concrete bridge will be replaced with a two-lane concrete and steel structure at an estimated cost of $5,074,739 + HST. The cost was approved as part of the City’s capital budget for 2024.

Porcupine River Bridge replacement was prioritized by Council after safety concerns shut down the bridge in November 2021. Since then, the City has streamlined design work and necessary approvals to award the final construction contract early in the year to facilitate ordering of structural steel and materials.

Contractors will begin to stage the work site on Monday, March 4, 2024. The estimated completion date of construction is November 2024.