Connecting Link


Recent Posts
1  2  3  4 
The final downtown segment of the Connecting Link will begin with demolition of the overpass on Algonquin Blvd. E. Contractors are expected to mobilize the week of March 25 to start staging the area, with removal of the overpass beginning the first week of April. Dates are subject to change.

Once Stage 1 of construction begins, Algonquin Blvd. E. will be closed east of the Spruce Ave. intersection to just east of the overpass, with traffic being diverted on Brunette Rd., down Second Ave. to Mountjoy St. S. Removal of the overpass is expected to take two weeks. This year’s detour route will see temporary traffic lights added at both ends of Second Ave., but the stop signs at the intersections of Spruce and Balsam will remain in place.

“We worked with AECOM’s Transportation Department to revise last year’s detour and ensure the east and west stop signs on Second Ave. at Spruce and Balsam were not removed,” says Scott Tam, Director of Growth and Infrastructure. “We’re confident this will not create any significant congestion along the detour route, but will certainly alleviate some of the concerns raised from last year.”

Stage 2 of construction will begin immediately following the demolition of the overpass. Algonquin Blvd. E. will be closed to all traffic from east of the Balsam St. intersection to west of Brunette Rd. Detour signs will be in place before Mountjoy St. for eastbound traffic.

“Algonquin Blvd. will remain open between Mountjoy and Balsam, but we’re trying to encourage motorists to plan their route, “adds Tam. “If you are bypassing the downtown, consider turning at Mountjoy. It will create less congestion at the point of construction and keep traffic moving.”

During construction, access to Service Timmins at City Hall will be from Cedar St. N. via a temporary pedestrian walkway to the main entrance. A pedestrian crossing will also be maintained across Algonquin Blvd. that will shift around the active construction area as work progresses. It’s important that residents obey signs and traffic controls to keep themselves and contractors safe at all times.

The City’s Engineering Dept. is also working with the local snowmobile club to minimize disruption to what has already been a short season. While the City anticipates that work will begin at the end of March, plans can change. Residents can sign up to receive Connecting Link updates directly at: www.timmins.ca/our_services/news_and_alerts/subscribe-to-city_news-alerts.

Work is also confirmed this summer for both bridges along the Connecting Link. Porcupine River Bridge and Mattagami River Bridge will be rehabilitated with temporary lane reductions beginning sometime in May. Contractors will begin site preparation in late March, which includes installing netting underneath the Porcupine River Bridge to deter nesting birds.

For more information on the Connecting Link, visit: www.timmins.ca/our_services/engineering/connecting_links.
Posted by Amanda Dyer  On Feb 28, 2024 at 12:31 PM
  
With Connecting Link construction wrapping up for the season, the temporary detour in place along Brunette Rd. and Second Ave. will be removed. Algonquin Blvd. E. is expected to open early the week of November 13, 2023. The City’s Traffic Dept. is prioritizing the replacement of stop signs along Second Ave. at the intersections of Spruce St. S. and Balsam St. S. Motorists should be prepared to stop on Monday, November 13.

Both intersections along Second Ave. will be returned to an all-way or 4-way stop with all motor vehicles on approach coming to a complete stop. At a 4-way stop, the first vehicle to come to a complete stop has the right-of-way. If two or more cars stop at the same time, right-of-way goes to the vehicle on the right.

This year, construction has been completed on Connecting Link Segment 6 through the Mountjoy intersection, Segment 7 from Mountjoy to just east of Balsam St. N., and Segment 2 on Riverside Dr. from Shirley St. to Government Rd. The downtown segments of the Connecting Link are part of a three-year contract, with construction on Segment 8 beginning next spring. Segment 8 will include the removal of the underpass on Algonquin Blvd. E. and the addition of a dedicated snowmobile crossing just east of Brunette Rd.

Sign up for Connecting Link updates today at Timmins.ca and stay up-to-date on the latest construction news.
Posted by Amanda Dyer  On Nov 09, 2023 at 10:27 AM
  

Connecting Link work continues at two construction zones in the city.

Segment 2 – Riverside Dr. from Shirley St. to Government Rd. – We anticipate Riverside Dr. will be open by early October. Contractors are finishing concrete this week and will move to paving the base and binder layers on the southside of Riverside Dr. Work will then move to surface paving, line painting, and electrical.

Segment 7 – Algonquin Blvd. E from Mountjoy St. to Cedar St. -  Contractor is completing pipe installation from Birch to Balsam. Curbs from Mountjoy to Birch are scheduled to start next week. The project will wrap up between Balsam and Cedar this year, with Algonquin re-opening late fall. Next year’s work will continue to just west of the Brunette intersection and includes removal of the overpass and installation of a new dedicated crossing for snowmobiles and pedestrians adjacent to Hollinger Park.

For more information on Connecting Link construction, visit: www.timmins.ca/connecting_link


Posted by Amanda Dyer  On Sep 15, 2023 at 12:38 PM
  
Contractors for the Connecting Link are wrapping up line painting on Algonquin Blvd. between the Mattagami Bridge and Mountjoy St. intersection this week.

Work on Segment 7 continues with blasting of the storm and water trench, which will facilitate installation of underground infrastructure.

Crews on Segment 2 of the Connecting Link between Shirley St. and Government Rd. have started work on catch basins and concrete installation on the south side of Riverside Dr. Beginning next Tuesday, August 08, work will move to the Walmart and Emerald St. intersection and include culvert replacement, lighting upgrades, and asphalt preparation. Work is anticipated to happen over 2-3 days. The entrance to Walmart will be kept open at all times with minor lane reductions.

Commercial motor vehicles are reminded that the detour along Shirley St. to Laforest Rd. remains in effect.

The City of Timmins thanks residents and business owners for their continued patience as we work through a busy construction season.
Posted by Amanda Dyer  On Aug 01, 2023 at 2:39 PM
  
City contractors working on Algonquin Blvd. are almost ready to wrap up Segment 6 and move forward on Segment 7 of the Connecting Link. Once crews have Mountjoy St. intersection reopened to traffic, work will progress up Algonquin Blvd. towards Cedar St. Motorists are being asked to divert down Brunette Rd. to Second Ave. back to Mountjoy St. S. to avoid construction. Mountjoy St. intersection could be open as early as Friday, but will most likely see traffic on Monday.

The new detour will move vehicles south of Algonquin Blvd., along one route that is designed to move traffic efficiently around a downtown construction area that is short on space. This is the second year of construction on a three-year plan that will replace crucial and aging infrastructure below the road surface.

“Segment 7 of the Connecting Link runs east of the Mountjoy intersection to just west of Cedar St.,” says Scott Tam Director of Growth and Infrastructure. “The work area is narrow and requires full-depth reconstruction of the roadway, replacement of underground services like water, sanitary sewer and storm sewer, and pole relocation. We’ve simplified the necessary detour to one route and optimized traffic control staging to keep vehicles moving.”

Contractors have added a temporary traffic light at Brunette Rd. and Second Ave. to allow more vehicles to make the left turn onto Brunette when heading east. The stop signs at Spruce St. S. and Second Ave. and at Balsam St. S. and Second Ave. will also be temporarily removed to prioritize traffic moving east and west.

“We will also review and adjust light timing at Cedar St. and Pine St. along Second Ave. if necessary,” adds Tam.

The City and contractors are working with Timmins Police Service to issue traffic advisories for the new detour route and temporary traffic controls. Once Mountjoy St. intersection is open, the temporary 4-way stop at Vimy Ave. and Theriault Blvd. will be removed. The 3-way stop at Vimy Ave. and Mountjoy St. N. will stay in place, now that a permanent stop for that intersection has been approved by City Council.

For more information on Connecting Link construction and to subscribe for Connecting Link updates, visit www.timmins.ca/connecting_link.
Posted by Amanda Dyer  On Jul 05, 2023 at 3:55 PM
  
Connecting Link construction is moving quickly on Riverside Dr. The contractor has been paving the inside lanes this week. Once complete, traffic will be diverted from the outside lanes to the inside lanes. We anticipate that this will happen early next week. Continue to follow signs and traffic controls.

Work on the outside lanes will include the installation of a new sidewalk from Shirley St. to Government Rd.

Crews have been in town this week pouring concrete for curbs and sidewalks in Segment 6 between Wilcox and Mountjoy. Once the concrete is poured, they do need to be covered and cure for 7 days before paving can begin. Once paving is complete, traffic controls are hooked up, line painting is finished, and Algonquin Blvd. from Preston through the Mountjoy intersection will be fully re-opened to traffic. We anticipate that this will happen in approximately 2 weeks, but will keep you updated.

Once construction moves to Segment 7 east of Mountjoy to Cedar St., vehicles will be diverted down one identified detour along Brunette Rd. to Second Ave. continuing to Mountjoy St. S. This a simplified detour route. Temporary traffic lights will be operational at Second and Brunette to maintain traffic flow. Motorists should also expect increased traffic along Sixth Ave. We will advise the public on the date the detour will go into effect.

Commercial motor vehicles are reminded that the detour along Shirley St. to Laforest Rd. remains in effect. Government Rd., Jaguar Dr., and Sandy Falls Rd. are not designated as truck routes.

This has been a busy construction season, but over the next couple of weeks, you’ll see a few projects wrap up and Connecting Link construction move ahead. Thank you for your continued patience.
Posted by Amanda Dyer  On Jun 23, 2023 at 8:25 AM
  

Work continues on Segment 6 of the Connecting Link between Wilcox St. and the Mountjoy St. intersection. All installation of in-ground pipes and infrastructure is completed. Crews will start to backfill the road, install curbs, concrete work, and traffic signals before paving and line painting can begin.

The contractor has also started on minor excavation and sign staging on Segment 7 east of the Mountjoy intersection to Cedar St. Once the Mountjoy intersection is fully reopened to traffic, crews will reopen Algonquin between Preston and Mountjoy and the detour along Brunette Rd. to Second Ave. will go into effect. The City will provide date and time.

We have been asked about the closed section between Waterloo and Preston. This area is part of the construction zone and is closed for motorist safety. The contractor uses this section as an access point for trucks and material delivery. We are anticipating that this will be open mid to late June.

Work is also being completed on the middle lanes of Segment 2 from Shirley St. to Government Rd. Traffic is currently reduced to one lane in both directions. Asphalt has now been removed. Crews will be removing existing concrete medians and doing some minor excavation before applying a layer of granule, new pavement, and installing new curbs and sidewalk.

The City continues to monitor traffic flow through the construction zone to prioritize vehicles moving east and west.

Commercial motor vehicles are reminded that the detour along Shirley St. to Laforest Rd. is now in effect. We have asked Timmins Police Service to take a more proactive approach in enforcing trucks bypassing the detour down Jaguar, Government or Sandy Falls. These roadways are not designated truck routes and heavy traffic can impact road conditions.

Thank you for your continued cooperation and patience as we expedite Connecting Link construction and complete work this season.


Posted by Amanda Dyer  On Jun 05, 2023 at 2:57 PM
  

Please be advised that Riverside Dr. between Shirley St. and Government Rd. has now been reduced to one lane in each direction, with traffic moved to the outside curb lanes while contractors begin work on Segment 2 of the Connecting Link.

In Segment 2 of the Connecting Link, work will be completed west of the Shirley St. intersection to Government Rd. In addition to stripping existing pavement, grading and compacting the base, and re-applying a fresh layer of asphalt, work will include installation of a cement sidewalk between Shirley St. and the Government Rd. intersection.

All access points and entries to roads and businesses along Riverside Dr. will be maintained throughout construction.
Motorists can expect delays and traffic congestion. Commercial vehicle trucks will still use the Shirley St. turn to connect with the standard truck detour along Laforest Rd. Some pavement milling in the outside curb lanes will be carried out to smooth entry points into adjacent roads and business entries.

Rehabilitation of the City’s Connecting Link is important work to improve major road infrastructure for Timmins. We appreciate your cooperation and patience as construction is completed.

Posted by Amanda Dyer  On May 23, 2023 at 2:15 PM
  
City contractors for Segment 2 of the Connecting Link along Riverside Dr. will be onsite placing traffic controls, staging, and surveying next week. Construction is anticipated to start after the May long weekend. Traffic will be reduced to one lane of traffic in each direction for the duration of work. All access points and entries to roads and businesses along Riverside Dr. will be maintained throughout construction.

In Segment 2 of the Connecting Link, work will be completed west of the Shirley St. intersection to Government Rd. In addition to stripping existing pavement, grading and compacting the base, and re-applying a fresh layer of asphalt, work will include installation of a cement sidewalk between Shirley St. and the Government Rd. intersection. This segment requires less infrastructure rehabilitation and excavation, so work is expected to move quickly.

The first stage of construction will concentrate on the middle three lanes, including the dedicated left turn lane, with traffic moving to the outside curb lanes. Motorists can expect some delays and traffic congestion, but no lengthy road closures. Commercial vehicle trucks will still use the Shirley St. turn to connect with the standard truck detour along Laforest Rd. Some pavement milling in the outside curb lanes will be carried out to smooth entry points into adjacent roads and business entries.

This is the second Connecting Link project this season and, with the addition of a dedicated pedestrian sidewalk, will make improvements to Timmins active transportation corridor. The City of Timmins appreciates the cooperation and patience of residents and motorists using detours and navigating lane restrictions as we carry out over $25 million in road repair work over the next few months.

For more information on Connecting Link construction and to subscribe for Connecting Link updates, visit www.timmins.ca/connecting_link.
Posted by Amanda Dyer  On May 12, 2023 at 1:42 PM
  
City Council has approved a second segment of Connecting Link construction this summer, which means the west end of Timmins will be getting a sidewalk along a busy stretch of Riverside Dr.

The unanimous approval to move forward with rehabilitation of Segment 2 of the Connecting Link, will see work completed west of the Shirley St. intersection to Government Rd. In addition to stripping existing pavement, grading and compacting the base, and re-applying a fresh layer of asphalt, work will include installation of a cement sidewalk between Shirley St. and the Government Rd. intersection.

This stretch of Riverside Dr. has been a topic of conversation, with increased foot traffic running between the Timmins Square retail mall and the busy Walmart corner. A sidewalk will improve safety and make accessing commercial properties along Riverside Dr. more accessible.

Motorists can expect lane reductions as construction work moves north and south, with possible congestion, but no lengthy road closures. Commercial vehicle trucks will still use the Shirley St. turn to connect with the standard truck detour along Laforest Rd.

This is the second stretch of the Connecting Link being completed this summer. Additional funding from the province’s Ministry of Transportation means that the work schedule has been moved up. Road closures for Segments 6 and 7 are already in place along Algonquin Blvd. west of Elm St. and east of Preston St.

For more information on Connecting Link construction, visit www.timmins.ca/connecting_link.
Posted by Amanda Dyer  On Apr 26, 2023 at 1:52 PM
  