Connecting Link update for August 30, 2022. Crews are currently working on the intersection at Preston St. All new infrastructure at Preston St. and Algonquin Blvd. is complete. Crews will start the disinfection procedure on the new watermain system this week. Hydro One will be moving services from old utility poles to new poles within the work zone. Once this is complete, the old utility poles will be removed and crews will complete the subdrains and start preparing for curb and sidewalk installation from just east of Theriault Blvd. to Preston St.
Work in the Beer Store parking lot has been finished and paving is being scheduled.
As we head towards the Mountjoy intersection, we are expecting to hit bedrock and may have to blast. You can see some of the existing rock formation on Algonquin by the Senator Hotel. A pre-blast survey has been completed by the contractor with all area businesses and residents in the area.
Finally, with the downpour we got last night, crews had some minor pumping of the excavation site this morning, but it won’t have impact on work progress.