Work is proceeding along segment 6 of the Connecting Link, which runs from Mountjoy St. to Theriault Blvd.

This week, crews are completing sidewalks, some soft restoration, and feathering in paving on side streets. Next week, electrical is scheduled (traffic signals and street lights). Line painting is also planned.

We anticipate that the remaining work will take approximately 3 weeks to complete. Algonquin Blvd. will be fully opened from Mountjoy St. to Theriault Blvd. at that time. 

Posted by Amanda Dyer On 11/8/2022 at 12:03 PM  

 