Connecting Link work continues at two construction zones in the city.
Segment 2 – Riverside Dr. from Shirley St. to Government Rd. – We anticipate Riverside Dr. will be open by early October. Contractors are finishing concrete this week and will move to paving the base and binder layers on the southside of Riverside Dr. Work will then move to surface paving, line painting, and electrical.
Segment 7 – Algonquin Blvd. E from Mountjoy St. to Cedar St. - Contractor is completing pipe installation from Birch to Balsam. Curbs from Mountjoy to Birch are scheduled to start next week. The project will wrap up between Balsam and Cedar this year, with Algonquin re-opening late fall. Next year’s work will continue to just west of the Brunette intersection and includes removal of the overpass and installation of a new dedicated crossing for snowmobiles and pedestrians adjacent to Hollinger Park.