Location: Evans St.
Value: TBD
Contractor: TBD
Completion: 2025
Status: Tendered
Project Manager: Scott Collin
Project Details:
Evans Street Bridge (TE-5) is located in South Porcupine, approximately 200m south of Golden Avenue. TE-5 is a 2-lane bridge that consist of a concrete/timber composite deck with 6 spans and has a total deck length of 40.1m. The structure is inspected on an annual basis by a consulting engineer as part of the City’s Ontario Structure Inspection Manual (OSIM) inspection program. The OSIM bridge inspection recommends a full replacement due to the overall poor condition of the structure. The consultant will go through the permitting process, complete a design and provide contract document for this bridge to be replaced in 2025/2026.